1- Front End Engineering Design (FEED) for Meahr-2, Pakistan | |
Client: | OMV Pakistan. |
Year: | 2012 |
Capacity | 30 MMSCFD Gas, 4500 BPD Condensate & 850 BPD Water |
Scope: | Design basis, simulations, equipment sizing, P&IDs development, packages specifications/datasheets, plot plan, operating philosophy, CAPEX, OPEX |
2- Front End Engineering Design (FEED)of Condensate Stabilization Mehar-2 | |
Client: | OMV Pakistan. |
Year: | 2012 |
Capacity | 1500 BPD |
Scope: | Design basis, simulations, equipment sizing, P&IDs development, packages specifications/datasheets, plot plan, operating philosophy, CAPEX, OPEX |
3- Fuel Gas Treatment Unit – Bayoot Field Yemen | |
Client: | Enerflex Middle East Ltd. |
End User: | Dove Energy Ltd., Yemen |
Year: | 2013 |
Capacity | 3.0 MMSCFD FGTU comprising of Inlet Separation, Feed Gas Compression, HCDP Control, Condensate Stabilization, MEG Injection and Propane Refrigeration |
Scope: | Process: Complete design which included Simulation and all Process deliverieables including P&IDs, Design Basis, Equipment Sizing design, Datasheets, Blow down Study, Equipment & Line list, Utility consumption, Contorl & Shutdwon Narrative. Piping & Mechanical: Complete piping design including Piping Material Specifications, Plot Plan, 3D modeling, Skid structural design, Piping MTO & fabrication isometrics. Civil: Skid structural dwgs with foundatoin design dwgs. C&A: Complete design including Design Philosophy, Control System Specification, Instrument procurement inquiries, Cause and effect. F&G detectors, Instrument Datahsheets, I/O Count & Instrument Index. Electrical Load List. |
4- De-bottlenecking Study of Kandanwari Gas Plant, Pakistan | |
Client: | OMV Pakistan |
Year | 2013 |
Capacity | 250 MMSCFD Gas |
Scope: | De-bottlenecking study to identify the bottlenecks to increase the capacity from 230 MMSCFD to 250 MMSCFD. Study included detailed evaluation of existing facilities, identification of bottlenecks, analysis of existing problems, process simulation, lines hydraulics, vessels and equipment rating, evaluation of alternatives, sensitivity analysis, energy analysis and cost estimation |
5- Kausar Field Gas Development Project, Pakistan | |
Client: | Descon Integrated Project (Pvt.) Limited |
Year: | 2013 |
Capacity | 33.0 MMSCFD |
Scope: | Process design verification of amine sweetening and gas dehydration units already installed for new process conditions. Study included process simulations, lines rating, equipment rating, material selection |
6- Early Production Facility – Standard Design | |
Client: | Schlumberger, Dubai |
End User: | HKN Energy Ltd. |
Year: | 2013 |
Capacity | 10,000 BPD Oil Sweetening and Stabilization Facility |
Scope: | Process: Complete design which included P&IDs, Process Flow Scheme, Blowdown & Flare Network Analysis, Hydraulic Analysis Report, PFDs & UFDs, Equipment & Line List, Utility consumption. Piping & Mechanical: Complete piping design including Plot Plan, 3D model, Piping Layouts, Fabrication isometrics, Piping MTO. Civil: Civil foundation design, Pipe Sleepers design. C&A: I/O List, Instrument Index, Instrument JB Schedule, JB termination dwgs, Cable Block Diagram, JB Layout. Electrical: Cable Sizing Calculation, Cable Schedule, Single Line Diagram, Wiring Diagram, Hazardous Area Classification, Load List, MTO, Earthing Layout. |
7- Concept Study of Mehar Gas Reinjection to Wellheads for Enhanced Oil Recovery, Pakistan | |
Client: | OMV Pakistan |
Year: | 2013 |
Capacity | -- |
Scope: | Concept study includes identification of potential location for compression and processing Units, analysis of available options and option selection, compressor selection, material selection study, cost estimation |
8- Stanley Liquids Recovery Gas Plant, Papua New Guinea | |
Client: | Enerflex Energy Systems Inc., Houston |
EPC Contractor: | Equinox Engineering Ltd., Canada |
End User: | Horizon Oil |
Year: | 2013 |
Scope: | Basic engineering of 2x75 MMSCFD Gas Mercury Removal Units and 2x2450 BPD Condensate Mercury Removal Units. The scope includes control valves/PSV sizing, P&IDs, equipment datasheets, instrument datasheets, piping layouts |
9- Miran Oil Early Production Facility, Iraq | |
Client: | Schlumberger, Dubai |
End User: | GENEL Energy INTL Ltd. |
Year: | 2014 |
Capacity | 10,000 BPD Oil Sweetening and Stabilization Facility |
Scope: | Process: Complete design which included Process Simulation, P&IDs, PFDs & UFDs, Hydraulic Analysis Report, Equipment Sizing & List, Datasheets, Utility consumption. Piping & Mechanical: Complete piping design including Plot Plan, 3D model, Piping GA dwgs for Fabrication, Piping MTO. C&A: Cause & Effect, Instrument Layout, F&G detector layout, IA Consumption, Cable Schedule, JB Schedule, Instrument List & MTO. Electrical: Load List, Single Line Diagram, Hazardous Area Classification, MTO. |
10- Far West Gas Compression Facility | |
Client: | Enerflex Middle East Ltd. |
End User: | OXY Oman |
Year: | 2014 |
Capacity | 15.0 MMSCFD Gas Compression Facility c/w all Utilities |
Scope: | Process: P&IDs, Cause & Effect, PFDs, Flare KO Drum & BDV Sizing. Piping & Mechanical: Complete piping design including Plot Plan, 3D model, Piping Layouts, Fabrication isometrics, Flare T-Support dwgs, Piping MTO. Civil: Complete Civil design including Equipment Civil foundation design, T-Rack structure & foundation design, Pipe Sleepers design, Trench Layouts, Civil MTO. C&A: I/O List, Instrument Index, F&G Detectors Layout & MTO. Electrical: Cable Sizing Calculation, Cable Schedule, Single Line Diagram, Cable Routing Layout, Wiring Diagram, Hazardous Area Classification, Load List, Electrical MTO, Lighting & Earthing Layout, Typical Installation Diagram, Key Line Diagram. |
11- Banyu Urip Well Clean-up (EOE), Indonesia | |
Client: | Schlumberger, Dubai |
End User: | OXY Oman |
Year: | 2014 |
Capacity | 10,000 BPD Oil Sweetening and Stabilization Facility |
Scope: | Process: P&IDs, Line Sizing, Flare & Blowdown Sizing Study Report, N2 Inbreathing Calculation, CV & PSV Sizing. Piping & Mechanical: Plot Plan, 3D model, Piping GA dwgs, Fabrication Isometrics, Piping MTO. Civil: Equipment Foundations design, Pipe Sleepers, Pipe rack, Civil MTO. C&A: Instrument Index, Instruments Datasheets, Cause & Effect Diagram, Instruments Layout, Cable Schedule, Instruments MTO, I/O List, Alarm & Trip Set Point List, Typical Hookup dwgs, ESD Fire & Gas System layout. Electrical: Design Basis, Cable Schedule, Electrical Layouts, SLDs, Cable Sizing, Earthing Calculation, Load List, MTO, Electrical Equipment List. |
12- Remboue Field Early Production Facility (EPF), Gabon | |
Client: | Schlumberger, Dubai |
End User: | OXY Oman |
Year: | 2014 |
Capacity | 10,000 BPD Oil Sweetening and Stabilization Facility |
Scope: | Process: Process Simulation, Equipment Design Vetting, P&IDs, PFD, Hydraulic Analysis Report, Line List. Piping: Plot Plan, Piping Isometrics. Civil: Equipment Foundation Design, Shelters Structural Design. Electrical: Hazardous Area Classification Diagram. |
13- Tatweer Gas Compression Facility, Bahrain | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 3 Trains each of 52 MMSCFD Gas Compression Facility |
Year: | 2014 |
Scope: | Process design including process simulations, PFD / UFDs, P&ID development, equipment sizing/verification, utilities consumption, equipment list, line list, hydraulic study, flare study. Piping design including plot plan, isometrics, tank farm design, BOQs. Electrical design including cable sizing, earthing calculations, lighting layout, installation drawings, BOQs. Instrumentation design cable sizing, termination drawings, BOQs. Civil & structural design including equipment foundation, grading plan, roads, fencing, modular pipe rack design with analysis, BOQs. |
14- MWHT Plant Singue, Ecuador | |
Client: | Schlumberger, Dubai |
Capacity: | 10,000 BPD Oil Sweetening and Stabilization Facility |
Year: | 2015 |
Scope: | Process: Equipment Design Vetting, P&IDs, PFDs, Process Simulation, Hydraulic Analysis report, Manual Valve List. Piping: Plot Plan, 3D model, Piping MTO. C&A: Cause & Effect. |
15- OXY Khamilah Gas Compression Facility, Oman | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 40 MMSCFD Gas Compression Facility |
Year: | 2014 |
Scope: | Process design including process simulations, PFD / UFDs, P&ID development, equipment sizing/verification, utilities consumption, equipment list, line list, hydraulic study, flare study. Piping design including plot plan, isometrics, tank farm design, BOQs. Electrical design including cable sizing, earthing calculations, lighting layout, installation drawings, BOQs. Instrumentation design cable sizing, termination drawings, BOQs. Civil & structural design including equipment foundation, grading plan, roads, fencing, modular pipe rack design with analysis, BOQs. |
16- Orinoco Belt, Faja, Venezuela | |
Client: | Schlumberger, Dubai |
Capacity: | 20,000 BPD Oil Sweetening and Stabilization Facility |
Year: | 2016 |
Scope: | Process: Process Simulation, P&IDs, PFDs, Equipment & Line Sizing, Flare Sizing, Manual Valve List. Piping: Plot Plan, 3D model, Piping Layouts/GAs, Piping MTO. Civil: Pipe Sleeper Design. C&A: JB Schedule, Cable Schedule, Cable Block Diagram, Instrument Index, Instrument & cable routing, F&G Layout, I/O List, JB Termination Dwgs, MTO, Instrument Panel & JB Layout. Electrical: Cable Schedule, Cable Sizing, Load List, Hazardous Area Classification, MTO, Key Line Diagram, SLDs, Cable and Overhead Line Routing Layout, Earthing Layout. |
17- Block 62 Gas Compression Facility | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 100 MMSCFD Gas and 2600 BPD Condensate Facility |
Year: | 2016 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Condensate & Water Storage Tank Sizing, Datasheets, Material Selection Study, Line & Equipment List, H&M Balance, Utility Consumption List, HAZOP, Operation Control & Safeguarding Philosophy, Flare Load Summary, What If Analysis, Hot Oil Volume. Piping: Complete Piping Design including Plot Plan, 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Stress Analysis, Piping MTO, Tie-in Schedule, Pipe Supports Layouts, Dead-Leg Register. Civil: Complete Civil Design including Equipment foundation design, Pipe Sleepers, Foundation Layout Plan, Fencing & Gates, Field Pipe Supports, Trench Layout, T-Supports. C&A: Complete Design including Cause & Effect, Instruments Layout, ESD Fire & Gas System Layout, Datasheets, Instrument Index, Routing Layout, I/O List, Instrument List, Specifications, JB Schedule, Cable Schedule, MTO, Instrument Alarm & Set point list, Control System Architecture, JB termination drawings, Instrument Loop Diagrams. Electrical: Cable Sizing Calculation, Cable Schedule, Hazardous Area Classification, Cable Routing, Cable Schedule, Load List, MTO, Earthing & Lighting Layout, Key SLD, SLDs, Typical Installation dwgs, Cable & Trench Layout, Wiring & Interconnection Diagram, Arc Flash Study. |
18- Block 62 Gas Compression Facility – Process Packages | |
Client: | Enerflex Global KL Sdn Bhd |
Capacity: | 100 MMSCFD Gas Dehydration Unit and HCDP Control Unit, 2600 BPD Condensate and Unit |
Year: | 2016 |
Scope: | Process: Process Simulation, P&IDs, Pressure Drop Calculations. Piping: Complete Piping Design including 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Piping MTO, Tie-in Schedule, Pipe Supports Layouts. Civil: Complete Civil Design including Skid foundation design, Skid Structural Design & Fabrication Dwgs, Pipe Supports, Skid Lifting Arrangement Dwg. |
19- Umm Niqa Crude Stabilization Facility | |
Client: | Schlumberger Dubai |
Capacity: | 20000BBL/d Crude Treatment facility |
Year: | 2016 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, UFDs, Datasheets, Line & Equipment List, Utility Consumption List, HAZOP, Flare Net Study, Tank Inbreathing & Outbreathing Calculation, Hydraulic Analysis Report, Process Safeguarding Diagram. Piping: Plot Plan. C&A: I/O List, Datasheets, F&G Philosophy & Layout, System Architecture Drawing, Alarm and set point List, Instrument List, Instrument Index, Cause & Effect. Electrical: All Project Specifications review, Hazardous Area Philosophy & Classification Diagram, Load List, Typical Installation Details, Hazardous Material List. |
20- Sabriya Gas Facility | |
Client: | Schlumberger Dubai |
Capacity: | 160.0 MMSCFD Gas and 46000BBL/D Crude Treatment Facility |
Year: | 2017 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Condensate & Water Storage Tank Sizing, Datasheets, Line & Equipment List, H&M Balance, Utility Consumption List, HAZOP, Operation Control & Safeguarding Philosophy, Flare Load Summary, Process Safeguarding Diagram, Tank Inbreathing & Outbreathing Calculation. Piping: Plot Plan. Civil: Foundations Adequacy Check. C&A: I/O List, Datasheets, F&G Layout, Specification for PLC, HIPPS System Specifications, System Architecture Drawing, Alarm and set point List, Instrument List, Instrument Index, Cause & Effect. |
21- EPC For Wellhead Compression Pilot Project | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 20.0 MMSCFD Gas Compression Facility |
Year: | 2017 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Datasheets, Line & Equipment List, H&M Balance, Utility Consumption List, HAZOP & HAZID Report, Control Safeguarding Philosophy and Shutdown Narrative, Steady State Hydraulic Study Report, Process Safeguarding Philosophy, Flare Network Study. Piping: Complete Piping Design including Plot Plan, 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Stress Analysis, Piping MTO, Tie-in Schedule, Pipe Supports & Layouts, List & Datasheets for valves & special items, Demolition Layouts, TBEs. Civil: Complete Civil Design including Equipment foundation design, Pipe Sleepers, Foundation Layout Plan, Fencing & Gates, Field Pipe Supports, Trench Layout, T-Supports, Grading Plan. C&A: Complete Design including Design Basis, Cause & Effect, Instruments Layout, ESD Fire & Gas System Layout, Datasheets, Instrument Index, Routing Layout, I/O List, Instrument List, Specifications, JB Schedule, Cable Schedule, MTO, Instrument Alarm & Set point list, Control System Architecture, JB termination drawings, Instrument Loop Diagrams, Hookup Drawings, Fire and Gas Detection Philosophy, Cable Block Diagram, TBEs. Electrical: Cable Sizing Calculation, Cable Schedule, Hazardous Area Classification, Cable Routing, Cable Schedule, Load List, JB Schedule, MTO, Earthing & Lighting Layout, Key SLD, SLDs, Typical Installation dwgs, Cable & Trench Layout, Wiring & Interconnection Diagram, UPS Sizing Calculation & Datasheet, Transformer Sizing, Power System Study, NER Sizing, Power System Study, Relay Setting & Protection Coordination Study, TBEs. |
22- Arcadia Compressor Station 2 Power Station | |
Client: | Enerflex Ltd., Australia |
Capacity: | 5.0MW Power Plant |
Year: | 2019 |
23- Oxy Maradi Huraymah Depletion Compression | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 91 MMSCFD Gas Compression Facility |
Year: | 2019 |
Scope: | Process: Complete Process design including Simulation, Design Basis, PFDs, P&IDs, Line & Equipment Sizing, Instrument Sizing, Datasheets, Utility Consumption List, Line List, HAZOP Report, Material Selection Study, Relief and Blowdown Study Report, HAZID, Safeguarding Diagram, Control and shutdown Narrative, Manual Valve List. Piping: Complete Piping Design including Design Basis, Plot Plan, 3D Model, Material Specification, Piping MTO, Datasheets, Tie-in List, Piping Plans, Piping Isometrics, Stress Analysis, Pipe Supports.TOR for model review. Civil: Complete Civil Design including Design Basis, Specifications, Equipment Foundation design, Piping Support & T-support design, Overall Foundation Layout, Trench Layout, Sleepers Layout, Structural Design, Civil MTO. C&A: Complete design including Design Basis, Cause & Effect Diagram, Datasheets, Specifications, Control System Architecture, layouts, Project philosophy, Alarm & Set Point List, Cable Schedule, Instrument Index, IO Function List, JB Schedule, Modbus List, Instrument Panel and Main Cable Routing Layout, Typical Drawings, JB Termination Drawings, Instrument Loop drawings. Electrical: Complete design including Design Basis, Hazardous Area Classification, Load List, SLDs, Specifications, Datasheets, Cable Sizing Calculations, Cable and Trench Routing Layout, Lighting Layout, Earthing Layout, Wiring & Interconnection Diagram, Electrical Cable Schedule, Lighting Cable Schedule, MTOs. |
24- Gas Compression Facility | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 450 MMSCFD |
Year: | 2020 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Datasheets, Line & Equipment List, H&M Balance, Sparing Philosophy, Utility Consumption List, Control Safeguarding Philosophy and Shutdown Narrative, Steady State Hydraulic Study Report, Process Safeguarding Philosophy, Flare & Blowdown Philosophy, Overall Schematic Diagram, Sensitivity analysis, Suction & Discharge Piping Volume, Gap Analysis, Control & Shutdown Narrative, Piping: Complete Piping Design including Plot Plan, 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Stress Analysis, Piping MTO, Tie-in Schedule, Pipe Supports & Layouts, List & Datasheets for valves & special items, TOR of Model Review, Pipe Spring Hanger, Special Supports Data Sheet, Pipe Rack SLD, Firewater Layout, Standard Pipe Restraints, Civil: Complete Civil Design including Design Basis, Equipment foundation design, Pipe Sleepers, Foundation Layout Plan, Fencing & Gates, Field Pipe Supports, Trench Layout, Main Pipe Rack, Grading Plan, Trench Layout, C&A: Complete Design including Design Basis, Cause & Effect, Instruments Layout, ESD Fire & Gas System Layout, Datasheets, Instrument Index, Routing Layout, I/O List, Instrument List, Specifications, JB Schedule, Cable Schedule, MTO, Instrument Alarm & Set point list, Control System Architecture, JB termination drawings, Instrument Loop Diagrams, Hookup Drawings, Fire and Gas Detection Philosophy, Cable Block Diagram. Electrical: Cable Sizing Calculation, Cable Schedule, Hazardous Area Classification, Cable Routing, Cable Schedule, Load List, JB Schedule, MTO, Earthing & Lighting Layout, Key SLD, SLDs, Typical Installation dwgs, Cable & Trench Layout, Wiring & Interconnection Diagram, UPS Sizing Calculation & Datasheet, Transformer Sizing, Power System Study, NER Sizing, Power System Study, Relay Setting & Protection Coordination Study. |
25- Khulud Gas Development Project Phase 1 | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 95 MMSCFD Gas Sweetening Facility |
Year: | 2020 |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Material Selection Study, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Datasheets, Line & Equipment List, H&M Balance, Utility Consumption List, Control Safeguarding Philosophy and Shutdown Narrative, Process Safeguarding Philosophy, Flare & Blowdown Philosophy, Overall Schematic Diagram, Control & Shutdown Narrative, Drain Philosophy. Piping: Complete Piping Design including Design Basis, Plot Plan, 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Stress Analysis, Piping MTO, Tie-in Schedule, Pipe Supports & Layouts, List & Datasheets for valves & special items, Demolition Layouts, TOR of Model Review, Pipe Spring Hanger, Special Supports Data Sheet, Facility Layout Report, Firewater Layout, Standard Pipe Restraints, Civil: Complete Civil Design including Design Basis, Equipment foundation design, Pipe Sleepers, Foundation Layout Plan, Fencing & Gates, Field Pipe Supports, Trench Layout, Main Pipe Rack, Grading Plan, Trench Layout, C&A: Complete Design including Design Basis, Cause & Effect, Instruments Layout, ESD Fire & Gas System Layout, Datasheets, Instrument Index, Routing Layout, I/O List, Instrument List, Specifications, JB Schedule, Cable Schedule, MTO, Instrument Alarm & Set point list, Control System Architecture, JB termination drawings, Instrument Loop Diagrams, Hookup Drawings, Fire and Gas Detection Philosophy, Cable Block Diagram. Electrical: Cable Sizing Calculation, Cable Schedule, Hazardous Area Classification, Cable Routing, Cable Schedule, Load List, JB Schedule, MTO, Earthing & Lighting Layout, Key SLD, SLDs, Typical Installation dwgs, Cable & Trench Layout, Wiring & Interconnection Diagram, UPS Sizing Calculation & Datasheet, Transformer Sizing, Power System Study, NER Sizing, Power System Study, Relay Setting & Protection Coordination Study. |
26- DSJ Compression Project - OGDCL | |
Client: | ILF Pakistan |
Capacity: | Front End Compression Project |
Year: | Phase-1 near to completion |
27- Sadad EDF DBOOM Project | |
Client: | Enerflex Middle East Ltd. |
Capacity: | 10 MMSCFD Gas & 4070 m3/d Condensate Processing Facility |
Year: | At Commissioning Stage |
Scope: | Process: Complete Process Design which included Process Simulation, Design Basis, Equipment & Instrument Sizing, P&IDs, PFDs, PFS, Datasheets, Line & Equipment List, H&M Balance, Utility Consumption List, Control Safeguarding Philosophy and Shutdown Narrative, Process Safeguarding Philosophy, Flare & Blowdown Philosophy, Overall Schematic Diagram, Control & Shutdown Narrative, Drain Philosophy. Piping: Complete Piping Design including Design Basis, Plot Plan, 3D Modeling, Piping GA/Layout dwgs, Piping Fabrication Isometrics, Stress Analysis, Piping MTO, Tie-in Schedule, Pipe Supports & Layouts, List & Datasheets for valves & special items, TOR of Model Review, Pipe Spring Hanger, Special Supports Data Sheet, Facility Layout Report, Firewater Layout, Standard Pipe Restraints, Civil: Complete Civil Design including Design Basis, Equipment foundation design, Pipe Sleepers, Foundation Layout Plan, Fencing & Gates, Field Pipe Supports, Trench Layout, Main Pipe Rack, Grading Plan, Trench Layout, C&A: Complete Design including Design Basis, Cause & Effect, Instruments Layout, ESD Fire & Gas System Layout, Datasheets, Instrument Index, Routing Layout, I/O List, Instrument List, Specifications, JB Schedule, Cable Schedule, MTO, Instrument Alarm & Set point list, Control System Architecture, JB termination drawings, Instrument Loop Diagrams, Hookup Drawings, Fire and Gas Detection Philosophy, Cable Block Diagram. Electrical: Cable Sizing Calculation, Cable Schedule, Hazardous Area Classification, Cable Routing, Cable Schedule, Load List, JB Schedule, MTO, Earthing & Lighting Layout, Key SLD, SLDs, Typical Installation dwgs, Cable & Trench Layout, Wiring & Interconnection Diagram, UPS Sizing Calculation & Datasheet, Transformer Sizing, Power System Study, NER Sizing, Power System Study, Relay Setting & Protection Coordination Study. |